England Coast Path in the south of England

03/10/2019 0 By wildfeed

Published 31 March 2015
Last updated 3 October 2019 + show all updates

  1. 3 October 2019 Map and table updated to show South Hayling to East Head stretch is now at stage 4.
  2. 17 July 2019 Map and table updated to show that Calshot to Gosport stretch is now at stage 4.
  3. 20 June 2019 Map and table updated to show the Gosport to Portsmouth stretch is now at stage 4.
  4. 14 March 2018 Page updated to show Highcliffe to Calshot stretch is now at stage 4.
  5. 31 January 2018 Update table to show Isle of Wight stretch is now at stage 2/3.
  6. 27 September 2017 Updated page to show that East Head to Shoreham stretch is now at stage 4.
  7. 19 July 2017 Updated to show that Portsmouth to South Hayling stretch has reached stage 4.
  8. 30 June 2017 Updated page: work has started on the Isle of Wight stretch
  9. 28 October 2016 Updated page: work on Calshot to Gosport and Gosport to Portsmouth stretches has reached stages 2 and 3.
  10. 1 July 2016 Map updated to show that work has started on the Calshot to Gosport and Gosport to Portsmouth stretches of coast.
  11. 25 January 2016 Added updated map to show change to extent of the Portsmouth to South Hayling stretch.
  12. 23 October 2015 Map updated. Work has started on the Highcliffe to Calshot stretch.
  13. 25 September 2015 3 new stretches started
  14. 31 March 2015 First published.

Source